Nov 12, 2015  CEE

Europrim Shipping move gas processing plant to Tatarstan

Following negotiations that took place over several months, Europrim Shipping, member to Cargo Equipment Experts CEE for Romania, was chosen to be the Romanian partner for the conventional maritime and river shipment of a natural gas processing plant from Malaysia to Tatarstan, CSI.

With a total size of more than 45,000 cubic meters and weighing over 7,000 tons, all the parts of the factory were shipped by four ocean vessels from the port of Kuantan, Malaysia up to Constanta port, where the special projects team completed all the necessary formalities for safely reloading the parts on 9 river-barge vessels, for further transportation on the Volga to final destination Nizhnekamsk, Tatarstan.

Besides unloading and terminal handling, customs formalities, planning, preparing and optimising stowage plans, loading and lashing onto the river vessels, the Europrim team has provided full ship agency services to shipowners, so that operations were carried out with maximum efficiency despite the hostile weather, the out-of-gauge parts and the tight schedule.

The deadline set by the agreement to tranship the factory until the Volga river is frozen was fully met, confirming the commitment and professionalism of the Europrim Constanta special projects team.

www.europrim.ro
www.cargoequipmentexperts.com

europrim_2 europrim_4 europrim_5 europrim_6 europrim_7 europrim_8 europrim_9

Source:: Cargo Equipment Experts, CEE