Nov 8, 2017  WWPC

Conveyor Logistics manages Barapukuria cargo

Conveyor Logistics, member to the Worldwide Project Consortium (WWPC) for Bangladesh, handled the delivery of a boiler drum, deaerator and stator assembly for the Barapukuria power station in Bangladesh.

The components for the coal-fired thermal facility measured up to 27 meters in length and up to 199 tonnes. The cargo was unloaded from an ocean vessel at Mongla Port on flat barges before being transported through the river system from Mongla to Balashight.

From Balashight the Drum, Deaerator and Stator Assembly were transported by a self-propelled modular transport to the power plant area.

www.conveyor.com.bd
www.wwpc.eu.com

Source:: Worldwide Project Consortium, WWPC

Facebook Twitter LinkedIn