Dec 28, 2023  WWPC

Greek discharge operation of windmill parts by Cosmatos Group

The project experts from Cosmatos Group were contracted to arrange for safe discharge of windmill parts arriving on board MV Chipolbrok Pacific at Thessaloniki Port in transit to North Macedonia. This was the biggest vessel ever arrived at Thessaloniki port to discharge windmills!

The shipment comprised of:

  • 9 complete set of windmill parts with total volume 62000 cbm and weight 6500 ton
  • 219 units in one shipment
  • Heaviest unit generator 105 ton

The scope of work for the Cosmatos team included:

  • Unlashing/unwelding at Thessaloniki port
  • Offloading in tandem and single lift
  • Port arrangements for temporary storage at port designated area
  • Inward customs clearance formalities

Cosmatos wildmill discharge Cosmatos windmill discharge Cosmatos windmill discharge

www.cosmatosgroup.com
www.wwpc.eu.com

Source: Worldwide Project Consortium, WWPC